Math-they Have To 800 Bricks To Complete The Job. How Many Hrs After He Began Working Did They Finish The Job?
sergei cna lay 45 bricks per hour, his boss can lay 60 brick per hr. sergei has already been working for 3 hrs before his boss started working with him
heres the formula
135+(60+45)(x-3)
EX: how many bricks have they laid in 4 hrs?
135+(60+45(4-3)
240
question:
they must lay 800 bricks to complete the job. how many hrs after sergei began working did they finish the job?


Sergei can lay 45 bricks/hr
his boss can lay 60 bricks/hr
given that Sergie has already been working for 3 hrs. During that time he has laid 45 * 3 = 135 bricks
let t be the time it takes for them to finish laying 800 bricks since the time his boss joins him
135 + 45t + 60t = 800
105t = 665
t = 6 1/3 hrs OR 6 hrs 20 min
so the total time is 9 hrs and 20 min <== answer
135 + (60 + 45)(x – 3) =
135 + 105(x – 3) = n where x is the time in hours and n is the number of bricks
n = 135 + 105x – 315
n = 105x – 180
So if they’re laying 800 bricks
800 = 105x – 180
800+180 = 105x
980 = 105x
x = 980/105
x = 9.33
x = 9h 20 min
If you want to double check that:
800 bricks – 135 (sergei already laid) = 665 Bricks.
45/h + 60/h = 105/h
665/105 = t
t = 6.33 = 6h 20 min + 3 hours sergei has already been working = 9h 20 min
7 hours 12 minutes