Math-they Have To 800 Bricks To Complete The Job. How Many Hrs After He Began Working Did They Finish The Job?

By CNAGuide

sergei cna lay 45 bricks per hour, his boss can lay 60 brick per hr. sergei has already been working for 3 hrs before his boss started working with him
heres the formula
135+(60+45)(x-3)
EX: how many bricks have they laid in 4 hrs?
135+(60+45(4-3)
240
question:
they must lay 800 bricks to complete the job. how many hrs after sergei began working did they finish the job?

You can leave a response, or trackback from your own site.

Tags: , , , , ,

3 Responses to “Math-they Have To 800 Bricks To Complete The Job. How Many Hrs After He Began Working Did They Finish The Job?”

  1. Rec

    Sergei can lay 45 bricks/hr
    his boss can lay 60 bricks/hr
    given that Sergie has already been working for 3 hrs. During that time he has laid 45 * 3 = 135 bricks
    let t be the time it takes for them to finish laying 800 bricks since the time his boss joins him
    135 + 45t + 60t = 800
    105t = 665
    t = 6 1/3 hrs OR 6 hrs 20 min
    so the total time is 9 hrs and 20 min <== answer

    #56942
  2. always_c

    135 + (60 + 45)(x – 3) =
    135 + 105(x – 3) = n where x is the time in hours and n is the number of bricks
    n = 135 + 105x – 315
    n = 105x – 180
    So if they’re laying 800 bricks
    800 = 105x – 180
    800+180 = 105x
    980 = 105x
    x = 980/105
    x = 9.33
    x = 9h 20 min
    If you want to double check that:
    800 bricks – 135 (sergei already laid) = 665 Bricks.
    45/h + 60/h = 105/h
    665/105 = t
    t = 6.33 = 6h 20 min + 3 hours sergei has already been working = 9h 20 min

    #56943
  3. Jenna T

    7 hours 12 minutes

    #56944